PMI Construction Professional (PMI-CP) Exam Prep
Free practice questions

Free PMI-CP Practice Questions

10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.

Start the free practice test → ★★★★★4.9/5 from 2,400+ candidates · No signup

The PMI-CP exam has 120 questions and runs 3 hours 50 minutes.

These 10 free PMI-CP questions are organized by exam domain, so you can see how each part of the PMI Construction Professional (PMI-CP) blueprint is tested. Reveal the answer and explanation under each question.

Domain 1: Contracts Management 50% of exam

Question 1

During an occupied terminal refurbishment, the owner's authorized contract administrator directs an additional cable route in writing. The contract permits such directions before price is agreed, requires continued performance pending valuation, and has separate notice and recordkeeping requirements. The contractor accepts the technical solution but disputes the proposed allowance. The work can proceed safely. How should the contractor protect its position without breaching this procedure?

Show answer & explanation

Correct answer: C - Proceed under the directive, give the required notice, and keep separate records of the changed work.

Question 2

An estimator reports a P80 cost of $42 million for a rail depot. The Monte Carlo model treats structural steel, reinforcement and steel cladding price movements as independent, although the three estimates use the same steel-price index. Each package also has unrelated labour and fabrication uncertainties. The sponsor intends to use $42 million as the funding limit. What must be resolved before relying on that percentile?

Show answer & explanation

Correct answer: A - Represent the shared price exposure and rerun the model before using its confidence estimate.

Question 3

An Integrated Form of Agreement (IFOA) links the owner's, designer's and constructor's incentives to final project cost. A coordinated plant-room redesign would increase mechanical costs but produce larger savings in structural and electrical work. Equivalent performance, schedule and risk have been verified. The mechanical lead opposes it because that package would exceed its original target. Which commercial response fits the agreement?

Show answer & explanation

Correct answer: B - Support joint approval of the redesign and apply the agreed project-level risk-and-reward sharing mechanism.

Question 4

While two subcontractors prepare adjacent work areas, the temporary-works coordinator sees a shoring tower moving and fresh cracking at its base. Operatives are working beneath the supported deck. The principal contractor controls the area, but the subcontractors dispute responsibility for the tower. What takes priority during the next few minutes?

Show answer & explanation

Correct answer: D - Stop the exposed work, clear and secure the danger area, and obtain a competent assessment.

Question 5

Before ordering a switchboard, a contractor can buy a $24,000 factory inspection-and-correction package. Without it, there is a 30% chance of a defect reaching the site and causing $180,000 of rework; the package reduces that chance to 5%. A separate expected transport-damage cost of $18,000 is identical under either choice. Both choices meet safety and contractual requirements. Using expected cost alone, what is the financial case for the inspection?

Show answer & explanation

Correct answer: A - Approve it; the expected total cost is $21,000 lower.

Domain 2: Stakeholder Engagement 30% of exam

Question 6

'The plant room will be yours on Thursday,' the mechanical lead tells the electrical lead. Both have allocated competent crews. Mechanical means installation finished; electrical means inspected and cleared for cable pulling. What is missing from this Commitment-based Management promise?

Show answer & explanation

Correct answer: A - Mutually agreed conditions of satisfaction for the plant-room handoff.

Question 7

The owner and main contractor have agreed a night-time delivery plan for a city-centre project. Shopkeepers have little formal decision authority, but explain that the unloading area is their only route for early-morning stock deliveries. No statutory restriction is breached, and construction delivery times remain flexible. Before issuing the final plan, how can the engagement lead secure workable support?

Show answer & explanation

Correct answer: C - Test revised delivery windows with the affected businesses and incorporate workable access arrangements into the plan.

Question 8

The weekly Obeya meeting ends with polished progress charts and a growing list of unresolved handoffs. Attendees understand the clashes, but package representatives must seek approval elsewhere before accepting a revised sequence. The same decisions return the following week. To change the meeting's results rather than its appearance, the facilitator should:

Show answer & explanation

Correct answer: C - Arrange decision-maker attendance or obtain explicit delegation for the participating representatives.

Domain 3: Strategy and Scope Management 15% of exam

Question 9

A new research building records a Project Definition Rating Index (PDRI) score of 175 using the building-project instrument. Equipment utility requirements were marked 'not applicable' because the tenant had not selected its laboratory equipment. The laboratories will require utility services, but those requirements remain undefined. Which conclusion belongs in the scope review?

Show answer & explanation

Correct answer: D - The total may understate scope gaps; assess the utility requirements as undefined and rescore the element.

Domain 4: Project Governance 5% of exam

Question 10

A project's governance plan delegates approval of individual changes up to $75,000 and one working day of completion delay to the project manager, provided required outcomes and external approvals remain unchanged. A $46,000 substitution causes no completion delay, meets the other conditions, has completed technical and commercial reviews, and fits approved funding. The sponsor is unavailable until next week. Who should authorize this change now?

Show answer & explanation

Correct answer: B - The project manager, with the decision recorded under the delegated authority.

That's 10 of 1,030

The full bank has 1,020 more PMI-CP questions with explanations.

Continue in the free practice test →